Reviewed by Erik Newton, Esq., on November 8, 2026.
Key takeaways
- Settle the work letter before you sign the lease: who builds, what the allowance covers, and when rent starts.
- Florida requires a licensed contractor, and a contract with an unlicensed one is unenforceable by that contractor (s. 489.128, Fla. Stat.).
- A tenant who contracts for the work is the “owner” under Florida’s lien law, so the notice of commencement and the lien releases are yours to manage.
- No one may occupy the space before the certificate of occupancy (or a temporary one), and you must apply to register each X-ray unit with the Department of Health within 30 days after acquisition and before use.
- Under ADA Title III, landlord and tenant are both responsible, and the lease may divide the work between them.
Dental clinic construction gets planned around the floor plan. The legal documents decide when you can open and who pays when something slips.
A new or relocated dental office runs on four sets of them: the lease and its work letter, the construction contract, the permits, and the state approvals for your equipment. Signed in the wrong order, their dates and obligations do not line up.
The work letter decides who builds, who pays and when rent starts
The work letter is the lease exhibit that governs construction. Settle four questions in it first.
- Who builds. List the landlord’s work (the shell, utilities to the space) and yours separately, with a deadline for each side’s approval of plans and change orders.
- Who pays. The tenant improvement allowance is a number, but its conditions decide what it is worth: what it may be spent on, when and against which documents it is paid, and whether unused money is lost. An allowance that looks generous may still not cover dental plumbing and HVAC.
- When rent starts. Rent commencement can be tied to a fixed date, to delivery of the space, or to completion and the certificate of occupancy. The later the trigger, the more of the construction delay the landlord carries.
- What happens if it is late. Look for rent abatement for delay and an outside date after which you may terminate.
Read the surrender clause too: a duty to remove your improvements at the end makes lead-lined walls and plumbing a second cost. More is in dental office lease negotiation tips and on the startup dental practice page.
Check the contractor’s license before you sign the construction contract
A person must be certified or registered to engage in the business of contracting in Florida (s. 489.113(2), Fla. Stat.).
Section 489.128 puts the cost of skipping it on the contractor. A contract entered into by an unlicensed contractor is unenforceable in law or in equity by that contractor, and no lien or bond claim exists in its favor for the work (s. 489.128, Fla. Stat.). A business is unlicensed if it has no qualifying agent for the scope of the work, judged as of the contract’s effective date. The rule gives you leverage, not a finished office, so confirm the license and the qualifying agent before you sign.
Then match the construction contract to the lease:
- a completion date that lands before your rent commencement date, with a remedy if it slips;
- a price structure you understand, with change orders only in writing;
- the permits and inspections assigned by name; and
- payment requests tied to lien releases, with the final payment held for the contractor’s final affidavit.
If you have a lease draft and a contractor’s proposal on your desk, have them read together before you sign either one. Schedule a confidential consultation
As the tenant, you are the owner under Florida’s lien law
Under Florida’s construction lien law in chapter 713, a lessee who contracts for the improvements is an “owner” and must be listed that way on the notice of commencement, with a statement that the interest is a leasehold (s. 713.13(1)(a), Fla. Stat.).
Notice of commencement. Before work starts on an improvement whose direct contract price is over $2,500, the owner records a notice of commencement with the clerk and posts a copy at the site (ss. 713.02(5) and 713.13(1)(a)). If the improvement does not begin within 90 days after recording, the notice is void (s. 713.13(2)). The permit card itself warns that failing to record one may result in paying twice, and for a direct contract over $5,000 a copy goes to the building department before the first inspection (s. 713.135(1)).
Payments. With any progress payment, you may require the contractor’s affidavit, and lienors who are paid sign partial releases (s. 713.06(3)(c)). At the end, the contractor gives a final payment affidavit, and the owner must hold the final payment until it is furnished (s. 713.06(3)(d)). A lienor may record a claim of lien up to 90 days after its final furnishing (s. 713.08(5)).
The landlord’s interest. When a lessee makes an improvement under an agreement with the lessor, the lien also extends to the lessor’s interest (s. 713.10(1)). A lease that expressly prohibits that protects the landlord when the lease, a memorandum of it, or a notice of the provision is recorded before the notice of commencement (s. 713.10(2)(b)). If your lease has such a clause, you must tell your contractor, and a knowing or willful failure to do so makes the construction contract voidable at the contractor’s option (s. 713.10(2)(a)). Practice real estate generally is on the healthcare real estate page.
No patients until the building department and the state sign off
A dental fit-out differs from an ordinary office here: the regulations reach the walls, the gas lines and the drains.
Permits and the certificate of occupancy
Unless the law provides otherwise, it is unlawful to construct, alter, modify or repair a building in Florida without first obtaining a permit (s. 553.79(1)(a), Fla. Stat.). The code in force is the Florida Building Code, 8th Edition (2023), adopted by rule 61G20-1.001, F.A.C., and a 9th Edition is coming from the Florida Building Commission, so check which edition governs your application: the edition in effect on the date you apply governs the permit (s. 553.73(7)(d), Fla. Stat.). A building may not be used or occupied until the building official issues a certificate of occupancy (Florida Building Code, Building, s. 111.1).
Accessibility
Florida law adopts the federal ADA Standards for Accessible Design, with Florida’s own modifications, into the Florida Accessibility Code for Building Construction (s. 553.503, Fla. Stat.). Under ADA Title III, both the landlord and the tenant that operates the practice are responsible, and as between them the lease may allocate the work (28 C.F.R. 36.201(b)). When you alter an area containing a primary function, the path of travel to it and the restrooms and drinking fountains serving it must be made accessible too, to the maximum extent feasible. If doing all of it would be disproportionate, meaning more than 20% of the cost of the alteration to the primary function area, the path of travel must still be made accessible as far as it can be within that 20% (28 C.F.R. 36.403(a), (f) and (g)).
X-ray registration and shielding
You must apply to register each X-ray unit with the Department of Health within 30 days after acquisition and before use, and only DOH-registered providers may install or service it (rule 64E-5.511(2), F.A.C.; s. 404.22, Fla. Stat.). Where wall shielding is required, it must run without a break from the floor to at least 7 feet, and doors and windows must carry the same lead equivalent as the wall (rule 64E-5.502(2), F.A.C.). For intraoral units, each X-ray control must be placed so the operator can observe the patient and stand at least 6 feet from the patient and tube head and outside the useful beam, or behind a protective barrier (rule 64E-5.506(4)(b)). The rule’s pre-construction plan review covers installations using x-ray energies of 200 keV and above (rule 64E-5.502(2)(e)).
Nitrous oxide and sedation
The plumbing volume of the Florida Building Code requires nonflammable medical gas, inhalation anesthetic and vacuum piping systems to be installed, tested and labeled in accordance with NFPA 99, except portable systems and cylinder storage (Florida Building Code, Plumbing, s. 1202.1). To use nitrous oxide inhalation analgesia, a dentist must have a delivery system with fail-safe features and a 30% minimum oxygen flow (rule 64B5-14.003(4)(a), F.A.C.). If you will offer moderate sedation or general anesthesia, you must pass an initial office inspection before the permit issues (rule 64B5-14.007(2)).
Sterilization and amalgam
The Board of Dentistry’s sterilization rule sets procedures your sterilization area has to support: instruments are cleaned first by scrubbing or with an FDA-approved ultrasonic cleaner or instrument washer, and handpieces are sterilized after each use with heat and pressure or heat with a chemical method (rule 64B5-25.003(2)(d) and (3), F.A.C.). More is in infection control rules for Florida dental offices.
Under the EPA’s dental office rule, a practice whose first discharge to a publicly owned treatment works came after July 14, 2017 is a new source: it must run an amalgam separator or equivalent device and file a one-time compliance report within 90 days after it starts discharging, unless it neither places nor removes amalgam, in which case the report certifies that instead (40 C.F.R. 441.10(f), 441.20, 441.40 and 441.50). Practices limited exclusively to orthodontics, periodontics, prosthodontics, oral pathology, or oral and maxillofacial surgery or radiology are outside the rule (40 C.F.R. 441.10(c)), one way orthodontist office construction differs.
The order of signatures is the plan
A dental build-out is decided on paper first: the work letter before the lease, the license check before the construction contract, the notice of commencement before the first inspection, the X-ray registration before the first exposure, and the certificate of occupancy before the first patient. If you are opening or relocating a dental practice and have a lease or construction contract in front of you, have the documents reviewed together before you sign. Schedule a confidential consultation
Frequently asked questions
What permits do you need to build out a dental office in Florida?
You need a building permit before construction and a certificate of occupancy before the space is used. You must apply to register each X-ray unit with the Florida Department of Health within 30 days after acquisition and before use, and a sedation permit requires an initial office inspection.
Can a contractor put a lien on the landlord’s building for a tenant build-out?
It can reach the landlord’s interest when you make the improvement under an agreement with the landlord. A lease clause that expressly prohibits that protects the landlord if the lease, a memorandum of it, or a notice is recorded before the notice of commencement. If your lease has the clause, you must tell your contractor.
What happens if a contractor is not licensed in Florida?
A contract entered into by an unlicensed contractor is unenforceable in law or in equity by that contractor, and it has no lien or bond claim for the work. A business counts as unlicensed if it has no qualifying agent for the scope of the work. The rule does not affect your own right to enforce the contract.
Related reading
- Understanding Dental Practice Valuations: EBITDA, Add-Backs, and What Buyers Actually Pay
- Selling Your Dental Practice: The Pre-LOI Mistakes That Cost Sellers the Most
- Buying a Dental Practice: Where Buyers Get Burned and How to Avoid It
- Buying Dental Practices at Scale: Platform Risk, Compliance Drift, and Repeatable Deals
Practice area: Dental Practice Sale and Acquisition Attorney in Florida
This article is for informational purposes only and is not legal advice. No attorney-client relationship is formed by reading it.